## Sheet1 Change Order Number Date Description Cost increase Original Contract 1 2015-01-01 00:00:00 Revise contract per Governor Mapp 0 2 2016-01-01 00:00:00 Archeological testing required by VISHPO 0 3 2025-01-16 00:00:00 Additional Archeological testing required by VISHPO 0 4 2017-02-01 00:00:00 Surcharge testing 0 5 2025-02-17 00:00:00 Revise SOV to reflect Surcharge testing 6 2018-01-01 00:00:00 Surcharge testing after Maria 0 7 2018-04-01 00:00:00 Locate existing utilities 0 8 2018-09-01 00:00:00 Design pile foundation and install test piles 0 9 2018-12-01 00:00:00 Phase II Archeological testing 0 10 2019-02-01 00:00:00 Change foundation to pile foundation 0 11 2019-07-01 00:00:00 Revise design for budget reasons 0 12 2025-07-19 00:00:00 Extend time due to Irma/Maria 0 13 2020-06-01 00:00:00 Revise budget for new design per Governor Bryan 7000000 14 2021-11-01 00:00:00 Memorialize agreed budget Supplemental Contract 0 15 2021-12-01 00:00:00 Time only for FEMA floodway issues 0 16 2022-11-01 00:00:00 Revise PEJ and TM bleachers from aluminum to concrete 0 17 2023-06-01 00:00:00 Change all interior walls from studs to block 0 18 2023-10-01 00:00:00 Add time for bleachers and sewer relocation 0 19 2024-01-01 00:00:00 Add design changes via supplemental Contract 2 per Act 8781 5124000 20 2024-02-01 00:00:00 Time only to allow for processing of design changes costs 0 21 2024-03-01 00:00:00 Memorialize agreed budget Supplemental Contract per Act 8781 0 22 2025-01-25 00:00:00 Time increase while assessing FEMA Floodway delays 0 23 2025-02-25 00:00:00 Partial time increase due to FEMA Floodway delays 0 24 Pending Time increase to finalize FEMA floodway delays 0 Supplemental Contract 1 1 2022-11-01 00:00:00 Revise PEJ and TM bleachers from aluminum to concrete 0 2 2022-11-01 00:00:00 Add storage under TM concrete bleachers 0 3 2023-06-01 00:00:00 Time only for design revision and partial FEMA Floodway delays 0 5 2023-10-01 00:00:00 Change all interior walls from studs to block 0 6 2024-03-01 00:00:00 Memorialize agreed budget Supplemental Contract per Act 8781 0 7 2025-02-25 00:00:00 Partial time increase due to FEMA Floodway delays 0 8 Pending Time increase to finalize FEMA floodway delays 0 Supplemental Contract 2 1 Pending Time increase to finalize FEMA floodway delays 0