02-22-94 10:11AM P02 f~4Bf& MILLER, INC. Environmental Services Ground Water Engineering Hydrocarbon Remediation Education February 18, 1994 Mrs. Caroline Kwan USEPA - Region H 26 Federal Plaza - Room 737 New York, New York 10278 Re: Revised Schedule for Field Activities, Tutu Wells Site, St. Thomas, USVI. Dear Mrs. Kwan: On behalf of the Tutu Environmental Investigation Committee (TEIC) Geraghty & Miller, Inc. kindly informs you that due to delays in the contractual agreement with the drilling contractor, the start date for the drilling activities for the Phase n Remedial Investigation (RI) at the Tutu Wells Site has been postponed for Wednesday March 9, 1994. The site safety meeting will be conducted the morning of Tuesday March 8, 1994. The soil gas survey has also been rescheduled to begin mobilization Monday, February 28, 1994 due to delays in the drafting of site access agreements with the USVI Department of Justice and the Virgin Islands Housing Authority (VIHA). Geraghty & Miller trust these changes in schedule do not cause an inconvenience. We will keep you updated about any other changes as the scheduled dates approach. If you have any questions regarding this matter, please call. Sincerely, GERAGHTY & MILLER, INC. <* >- 'Xlberto Colberg / Senior Scientist/Fjfeld Coordinator Thomas V. Danahy SeniorSdgnlisl/ProjectManager L. Nachman cc: Ana Gloria Ramos (TEIC) Vice President/Project Officer Paul Ryan (Texaco) TUT 006 1277 809 Fernandas Juncos Avenue • Santurce, Puerto Rico 00907 • (809) 725-2304 • FAX (809) 725-2344 *64743* 64743