November 10, 1994 de inc. 186 Center Street Suite 290 Clinton, NJ 08809 (908) 735-9315 Fax (908) 735-2132 Caroline Kwan VIA FAX AND U.S. MAIL U.S.E.P.A. Region II 26 Federal Plaza, Room 737 New York, NY 10278 RE: Confirmation of Project Schedule Tutu Wells Site RI/FS Dear Ms. Kwan: Near the end of the project meeting on November 3, there was considerable discussion regarding the schedule for future deliverables and meetings. The following confirms TElC's understanding of the new schedule of deliverables and events based on the meeting and our subsequent telephone discussion. EPA Provides Soil and Groundwater Remedial Goals EPA Provides Final Comments On Rl Report and RATM To TEIC Meeting Between EPA and TEIC To Review Comments TEIC Submits Draft Final RATM TEIC Submits Draft Final Rl Report TEIC Submits Draft FS Report To EPA EPA Hold Public Availability Meeting (St. Thomas) PRP Meeting To Discuss FS Report (St. Thomas) PRPs Submit Comments On FS To EPA EPA Provides Final Comments On FS To TEIC Meeting Between EPA And TEIC To Review FS Comments TEIC Submits Draft Final FS Report To EPA EPA Issues Proposed Remedial Action Plan (PRAP) Public Comment Period (Assume 30 day duration) EPA Public Meeting On PRAP November 15, 1994 November 30, 1994 December 15, 1994 December 23, 1994 January 17, 1995 January 30, 1995 March 7, 1995 March 8-9, 1995 March 20, 1995 April 4, 1995 April 20, 1995 May 16, 1995 May 30, 1995 May 30 - June 30, 1995 Mid May, 1995 TUT OO6 0649 ' PAPER *64638* 64638 de maximis Ms. Caroline Kwan November 10, 1994 Page 2 EPA Signs ROD Special Notice Letters To PRPs Complete CD Negotiations With PRPs (Assume 120 days) Remedial Design Initiate Remedial Action (Construction) Sincerely, de maximis, inc. July, 1995 August, 1995 December, 1995 Jan. 1996 -Aug. 1996 September, 1986 Geoffrey C. Seibel Project Coordinator PRP Steering Committee PRP Technical Committee L. Reed/A. Shottroff, USVI DPNR FILE: 30B9 O4\CONFPRJ SCH TUT OO6 0650 ' PAH*