a> lee Jayson Parrilla CIP Project Manager. Virgin Islands Department of Public Works Government of the United States Virgin Islands 6002 Anna’s Hope. Christiansted, VI 00820 September 20, 2021 Subject: Letter of Justification for PE#31 Advance Payments Service Contract for the Design-Build of the Paul E. Joseph Sports Complex Contract No. CO03SPRC15 Dear Mr. Parrilla, As a result of the Covid-19 pandemic, construction materials worldwide that were readily available at the time the project was bid are now experiencing long lead times between the purchase date and the ship date. In the USVI GEC has been experiencing lead times of over 9 months for materials that would normally be available in 6 to 8 weeks. This long lead time causes extensive project delays. In order to ensure timely delivery of the materials needed to complete the Paul E. Joseph Stadium (PEJ) project, PE #31 contains billings for advance payments for the remainder of the majority of the materials needed for the next phase of the project. Purchasing the remainder of the materials needed for the PEJ project immediately is the only way to avoid future schedule changes as a result of these delays. Advance payments for materials is allowed under the terms of the Contract. Therefore, in order to avoid delays we ask that you approve PE#31 so that these materials may be ordered promptly. Sincerely, Sow Sb nme — Jon Adams, Project Manager Copy to: Derek Gabriel, Commissioner of VI Department of Public Works Calvert White, Commissioner of VI Department of Sports, Parks and Recreation Anthony D. Thomas, Commissioner of VI Department of Property and Procurement John Wessel, Managing Member, GEC Janis Persaud, Project Administrator, GEC GOVERNMENT OF THE VIRGIN ISLANDS OF THE UNITED STATES Department of Property and Procurement 8201 Sub Base, 3rd Floor, St. Thomas, U.S. Virgin Islands 00802 3274 Estate Richmond, Christiansted, U.S. Virgin Islands 00820 St.Thomas: | St. Croix: Main Office: (340) 774-0828 Main Office: (340) 773-1561 Fax: (340) 777-9587 www.dpp.vi.gov Memorandum: To: From: Date: Re: xC: Nathan Simmonds Director, Finance and Administration Virgin Islands Public Finance Authority Anthony D. th Ley D. Cheats Commissioner | Department of Property & Procurement February 24, 2022 Request for Payment to GEC, LLC Transmitted herewith for partial payment is Periodical Estimate No. Thirty-Three (33), for Construction Services rendered by GEC, LLC, for the Design/Build for Paul E. Joseph Stadium & Sports Complex, St. Croix, Virgin Islands as outlined in Contract No. C003SPRC15(GEC). Estimate Number Date P.E. #33 February 11, 2022 Funding Source: 2014C Gross Receipt Tax Bond Department of Sports, Parks & Recreation Department of Public Works Department of Property and Procurement Contract File ADTikp/te $168,513.84 GOVERNMENT OF THE VIRGIN ISLANDS OF THE UNITED STATES | Department of Property and Procurement 8201 Sub Base, 3rd Floor, St. Thomas, U.S. Virgin Islands 00802 3274 Estate Richmond, Christiansted, US. Virgin Islands 00820 St. Thomas: | St. Croix: Main Office: (340) 774-0828 Main Office: (340) 773-1561 Fax: (340) 777-9587 | www.dpp.vi.gov February 24, 2022 John R. Wessel Managing Member GEC, LLC P.O. Box 1656 Kingshill, VI 00851 RE: CO003SPRCI5 (GEC) Design/Build for Paul E. Joseph Stadium & Sports Complex, St. Croix, Virgin Islands Dear Mr. Wessel: Transmitted herewith approved is Periodical Estimate for Partial Payment Number Thirty-Three (33), dated February 11, 2022, and received on February 23, 2022, relative to the above referenced contract. The periodical estimate is the balance due on this contract in the amount of One Hundred Sixty-Eight Thousand, Five Hundred Thirteen Dollars and Eighty-Four Cents ($168,513.84). Respectfully, Aituy 0. Cora Anthony O/ Thomas Commissioner ADT p/tc xe: Department of Sports, Parks & Recreation Department of Public Works Virgin Islands Public Finance Authority Department of Property and Procurement Contract File VV February 22, 2022 Honorable Anthony Thomas Commissioner Department of Property & Procurement Building #1, Sub Base, 3rd Floor St. Thomas, U.S. Virgin Islands 00802 RE: COO3SPRC15{GEC} - Design-Build Pau! E. Joseph Stadium & Sport Complex in Estate La Grange, St. Croix, U.S. Virgin Islands Periodical Estimate No.33 Dear Commissioner Thomas: | am requesting your Agency's direct assistance in the expeditious processing and signature approval of Periodical Estimate No. 33 in the amount of One Hundred SixtyEight Thousand, Five Hundred Thirteen and 84/100 Dollars ($168,513.84). This request represents services performed under COO3SPRC15{GEC) Contract for the construction of the Design-Build Paul E. Joseph Stadium & Sport Complex in Estate La Grange, St. Croix, U.S. Virgin Islands between the Government of the Virgin Islands and GEC, LLC. This payment is compensation for continued construction on the concrete mat slab and walls for Paul E. Joseph Stadium. It is my recommendation that this payment be processed in accordance with GVI contractual obligations. If you have any questions and/or concerns, please do not hesitate to contact Chief Engineer, Tawana Nicholas, at (340) 773-290, Extension 2260 or Tawana.Nicholas@dpw.vi.gov. Respectfully, erak A. Ga 5 Commissioner Department of Public Works DAG/tan Attachments: Periodical Estimate No. 33 Stored Materials Summary Pay Estimate 33 Worksheet Change Order No. 10 Summary CC: Calvert White, SPR Commissioner DEPARTMENT OF PUBLIC WORKS ST. CROIX 340.773.1290 United States Virgin Islands . ST. THOMAS/ST. JOHN 340.776.4844 NAME OF PROJECT: GOVERNMENT OF THE VIRGIN ISLANDS: PEROOICAL ESTIMATE FOR PARTIAL PAYMENT Design-Build of Pow R. Joueph Stedim end Sports Compton LOCATION: BL Groks, Virgin laloncts MAME OF CONTRACTOR GEC, LLC Contract No. COOISPACIS{GEC) PERIODICAL ESTIMATE HO. 33 , 1 FOR PERIOD 44-16-71 90 2-11-22 PERSON AL ESTATE NO.21 ORIGINAL ESTIMATE COMPLETED To DATE. Value of Uncompleted % Com baton Cll Quantty | vaetinewes | Cost Per Unit Veue Nod Vaue Work planed iw @ o | (3) ® fu) a) o (10) A [Pre-Buspension Work to SHaN5 1 [insurance 1 is $ 1,013,675.00]$ 1.013,875.00| 10 /$ 1,013,875.00)$ - 100% 2 «(| Architectural and Engineering Fees 1 us $ 375,000.00} $ 375,000.00] 10 |$ 375,000.00 | $ o 100% 3 | Consulting & Permi Foes 1 us $ 107,12500]$ 107,125.00] 10 |% 407,125.00 | $ fs 100% 4 = |Contact and O p 1 u $ W0,000.00]$ 300,000.00] 10 | $5 300,000.00 | $ - 100% § [Demolition trough 3-16-15 1 us $ 650,000.00/5 650,000.00] 10 1$ 650,000.60 | $ - 100% 6 |Lead i c gency) 1 us $ 166,500.001$ 166,500.00) 10 |$ 186,500.00 | $ - 100% 7 jMobilation 1 1s $ 162,500.00]$ 162,500.00] 10 |$ 182,500.00 | $ - 100% Aa |Teue up mobilization to 10% of Contract 1 us $ 2,537,900.00 | $ 2,537.500.00] 1.0 /$ 2,537,500.00/$ 3 100% B [Paul E. Joseph Stedtum 1 [60% Design (ASE & Civil) - Permits/Approvals 1 ts $ 1,680,000.00 | $ 1,680,000.00] 1.0 | $ 1,680,000.00/3 - 100% 1a [80% Design 1 Ls $ 200,000.00/$ 300,000.00] 10 |S 300,000.00 | $ - 100% 1d |100% Design 1 uw $ 40,000.00] $ 40,000.00] 1.0 1S 40,000.00 | $ - 100% 1c | Administration During Construction 1’ Ls $ 105,000.00}$ 105,000.00) 0.1 |$ 69,300.00 | $ 35,700.00 x 1d [Design Changes CO 10 ($94,600) & CO11 ($05,200) 4 is $ 190,000.00]$ 190,000.00] 10 |S 190,000.00 | $ : 100% 1e [Additional Design Costs CO 13 4 is $ 612500.00/$ 612,50000] 10 |$ 612,500.00 | $ - 100% 2 = [Foundation (Test piles and pile design) 1 us $ 167,500.00|/$ 167,500.00] 10 15 167,500.00 | $ oS 00% 2a pe Earthwork ’ ss $ 960,000.00} $ 960,000.00] 1.0 /$ 960,000.00 | $ - 100% 2b [Surcharge Testing 1 ts |$ 100,000.00]$ 100,000.00] 1.0 |$ 100,000.00) 5 . 100% 2c $Pile Fourxtation 1 Lb: $ 3,702,300.00 | $ 3,702,300.00) 1.0 |$ 3.702,300.00/$ bd 100% 2d [Mal Slab Foundation 1 “B $ 3,466,850.00|$ 3,466,650.00] 06 $5 3,252,016.43/$ 213,733.57 eK 3. [Structural Steel and Concrete Superstucture ‘ is $ 1,603,634.26| 5 1,600,634.25] 0.0 |$ 1,005.750.00/$ $97,884.25 on 8 Locker Rooms & Showers 1 is $ 200,000.00] 200,000.00] 0.0 |$ 402,300.00 | § 97,700.00 51% 10 | Public Restrooms 1 Ls $ 250,000.00]$ 250,000.00] 0.0 |$ 474,800.00 | $ 76,200.00 7% 12 Entry Pavilion 1 is $ 136,000.00]$ 135,000.00) 0.0 |$ 66,000.00 | $ 49,000.00 om 15 |Party Deck Area 1 us $ 135,000.00/$ 135,000.00] 0.0 |$ 66,100.00 | $ 48,900.00 abel 19 [Dugouts ’ is $ 155,000.00} $ 155,000.00] 00 /$ 121,300.00 | $ 33,700.00 Te 20 |Stalways & Common Spaces 1 1s $ 330,000.00]3 330,00000) 00 /$ 145,000.00 | $ 185,000.06 un 25 [Mechanical 1 us $ 95,000.00} $ $6,000.00) 0.0 |S 60,000.00 | $ 35.000.00 6 26 jElectrical 1 “S $ 1,100,000.00 | $ 1,100,000.00 |: 0.0 | $ 544,821.50 | $ 655,178.50 on 28 [Plumbing ‘ uw $ 385,000.00)$ 385,000.00] 00 |$ 313,560.00 | $ 71,450.00 8% ¢ |TERRENCE MARTIN FIELD 1 160% Design (ASE & Civil) - Pacmis/Approvals 1 u $ 200,000.00/$ 200,000.00) 1.0 )$ 200,000.00 | $ - 100% ta [90% Design t us $ %,000.00)3 30,000.00] 16 /$ 30,000.00 | $ . 100% tb |100% Design 1 is $ 7,500.00 | $ 7,500.00] 0.0 |$ 7,500.00 | $ . 100% tc 1A During C 1 ls $ = 12,500.00} $ 12,600. 00 1$ -|$ 12,600.06 % Do ie CHRISTMAS VILLAGE 1 180% Design (ASE & Chil) - Penmits/Approvats 1 us S$ 138,000.00]$S 136,000.00) 10 /$ 136,000.00 | $ . 100% ja [90% 1 is $ 20,000.00] $ 20,000.00} 0.0 |$ 20,000.00 | $ - 100% ib 1100% Dasign 1 uw 5 §,500,00 | $ 5600.00] 0.0 | $ $500.00 | $ - 100% te JA During C 1 is $ 6,500.00 | $ 8,500.00] 0.0 |$ -|5 8,500.00 nm E {SITE IMPROVEMENTS 4 [60% Design (ASE & Ctull) - Permits/Approvals. 1 is $ 66,200.00) $ 65,200.00] 1.0 | $ $5,200.00 | $ - 100% ta 190% Design 1 us $ 110,000.00} 110,000.00] 00 1$ 110,000.00 | $ - 100% 1b | 100% Design i) is S$ 13,600.0055 13,600.00 | 0.0 |$ 13,600.00 | $ - 190% 1¢ During € 1 1s $ 46,200.00] $5 46,200.00] 0.0 | $ “1S 46,200.00 % 2 = [Earthwork & Grading 1 Ls $ 500,000.00/$ 800,000.00] 10 |$ $00,000.00 | $ - 100% 7 ~— |Site improvements 1 us S$ 232,606.25/$ 232,806.25] 1.0 |$ 232,806.25 | $ - 100% F [Demolition inci. Wall, Lights 1 us $ 200,000.00] $ 200,000.00] 10 /$ 200,000.06 | $ . 100%, G Owner's Contingancy 1 is |S 07,100.60/$ 87,109.50] 10 |S 87,109.50 | $ - 100% Extend Butider’s Risk to 10-31-19 1 is $__200,000.00/$ 200,000.00] 1.0 | $ 200,000.00 | $ : 100%. TTotats ra GEE $ 22,900,000.00 | St 3 20, 353.88 | $ 846.32 SCHEQULE OF CHANGE ORDERS APPROVED CHANGE ORDER COMPLETED TO DATE tenho | Decctionelem ——S*S*«&SC«C a | Com Per Unt Voke Tee Vee «ds Vekn ol Uncammpnesa % Come Meamere Unie Wer, pated () (2) tu] (4) it] (6) (ta @ to) (10) 1 Reviea Contrat from “Gunrentend 3 ~_ 1s : 4 $ - ja - 100% Maxdrusn Price” to Sunt. 2 § Flatd Work Phase @ Arch, $ - Is 5 4 - 48 = 00% 3 |aseetonat geotachnicsl wewetneton $ _Is os mz) ~ Is : 107% 4 Contem 60% Design, start 90% Oesign, 3 -~ 18 - 1 -~ Is - 100% Jupdate neurance and Bonds. Reviee SOA, |Sumpend Miestons Dates and Schedule, aeprove PE 8 Scheaute of amounts for contract = . 1 [$s ~ 4s 5 100%. Eartrvork = : 1 3 oe 3 z 400% Locate. Utes : . 1_sjs a : 100%. Tesi Plies and Wnitiel Earitwwort, $ . . 1 $ . $ . 100% 3 Phase 2 U ot Nebare 3 . $ . 7 s A $ 5 100% 10 [Puevmet sed, PE) 700 santa A -_ js : 1 |s - [8 . as uv and SOV bor reviand EY - 1s = + 18 = 1s : 10% 12__ [Extend tira, delete Gubders Rist % ~ js : 1 3 - is = On 13 |Reeae SOA per fina! 3_- A -_|s_ 2900,000.00T 1 - Is 5 o% 2 ANALYSIS OF ADJUSTED CONTRACT AMOUNT TO DATE a ‘Originet contract amount 3 70,000,000.00 8. Pius: Addliona i 990,000.00 | Cc. Less: Dedvetors. 0. Adpriied contraci amount in date = 22,900,000.00 3. ANALYSIS OF WORK PERFORMED + ‘Veiue of original contract work performed to date {Column 8 Front} (or add secand page if applicable} tJ 20, 2 Extra work performed in data 3 ‘Total velue of work performed to date 3 20,834,353.68 4 Ack Meteriete stored st dose of Pie Getadied } $ 101,850.00 S Less: Arreund retained a 427 352.91 6 Mel eerqund cerned on contract work to dete $ 20,508,850.77 7 Othe deductora 8 ‘Leas: Amourd of previous payments $ 20.440,336.92 ] BALANCE OVE THIS PAYMENT 3 168,533. 4, CERTIFICATION OF CONTRACTOR with the Texrns, al beween OF THE VIRGIN SLANOS ne SEC UC Gated tle 201. endéos uly suihortzed Seasons. subsiiLaions, allers bons, and/or addtions, thet te arvesd a wp era GEE, ULE & ~ {Contractor} dobn R., Vretssl 2-11-2022 = fae (Oote) $. CERTF | cartity that erihed this Estrate No. 33 for the pared of = 12/98/2021 trough rable e7d ancitive: Bust to the best of my knowtadge end betel ls tr. OF work, thet of work ends in tvs has b itor materia! supplied by te (het a6 work andor 3 hes been by iy thy Fepresentative oF semistants and thea R has been supplied in h tha Terms and Conditions of the construciian condract, drawings, plans and specticagona, endfor duly authorized devietors, substations. sone by Ine duly sulborized egent of ta GOVERNMENT OF THE VIRGIN ISLANDS: oat ee Geren 4. LED ow Lf Ubf 202 (alae, _— Cotvert While. Comerissione: of Sports, Parks and Recreation Tawana Albany Nicholas stm nomsant= sous Dera 1d Public Works Engineer ‘ Mig Die caw 2/24/2022 ry C. Tharema, Of Viegin ialanats of Property and te A. mes OP 02.24.2022 CONCISE NT OF THE VIR @LAMDS Pipecter a, EATIAATE FOR PARTIAL PAYWEDT HAE OF PROECT: Dew pats of Pest. LocaTon: = yt saat OF COMTINCTOR Mut Convene. gramepmeswore ESTATE MO. n Ppa egr00 sarvecress ve $.19:32 ¥ * LJ © toon escripstion of Renn Vaio Sen-Vatve |] Compiote Completes | * Some pl | a cnrczed Retainage pexvioyes | thiePe | to dete * rutainege i [previously resensad| [A [Pro-Suapension torn to SHOE 1 |inewrence $ 1.013,876.00 100%. 100% |S 112,676.00 6 5.013.875.00 . 2 |Ncecural and Enginewing fees $ 37$,90000 100% 100% «| $ 00 $ 378,000.00 G 1 [Conmiling & Permi Fees S 107,125.00 00% 100% & = 07,125.00 3 107,123.00 . ‘ Oeveiopmart 200,00000 wr, 10% fs % 00 . 6 \Oememian trough 3-10-15 % #8000000 100% 100% | 6 esogonco 3 860,000.00 . @ fend Ahasemant $ 196,800.00 100% to% | $ 188,800.00 4 = $06,50000 : ? $ 162,800.00 100% 107% | $ t62,eo000 $ 962,800.00 . Ae [Tree up mobilization to 10% of Contract $ 2,537,500 00 10% tom | s 2.837,500.00 3 2.837,500.00 0 8 |Pawd. Joseph Stadhen . 1 [Oo Ossign (ARE & Covi Permitatigprova | 1,080,000,00 100% 100% | $ 1,080,000.00 sw 1a [90% Design % 900,000.00 00% 10% | % socoanc. $ $00,000.00 0 1% ]100% Design $ 40,000.00 100% 100% 16 49,000.00 s 40,900.00 o te [Administration Curing Consinztion 3 105,000.90 7m AOR om $ 21,00000/% 40,500.00 | $ 9200.00 5 4,900.00 V4 [Oenig Cranges CO 10 (364.000) § CON1 (905.200) $ 1900000 100% Dad $ 190,000.00 + 980,000.00 . te [Additonal Design Coste CO 13 $ #12,50000 100% 100% [3 6t2.sc000 6 612,600.00 . 2 [Rouretation (Twat pitas ond pile design} 3 1870000 100% tom [3 1er.sc0.00 $ 187,800.00 C a Casthucrte & 690,000.00 100%, 107% | 900,000.00 s =. gen.c0a00 0 Ze | Surcharge Testing $ 100,000.00 100% 107% ] 6 100,000.00 $ 192,000.00 . 2p [Pte Foundation $ 3,702,300.00 100% $OO% | $ 3.702,300.00 & © 3,702,20000 C 24 [heat amb Foundation $ 3,408,65000 17% | 300% wom «| 8 A02m.117.00]8 = 1z4,7one0] $ « 3282,.91043/5 —1TE.12K.76 2 nathatad Steed $ Lewes Xe [Coverete red rotar materiel $ 280,000.00} 100% won |$ 2000000] s - |% 200000018 — 28,000.00 3% |Concrmia ond ruber instalation $ 450,000.00 280% $ = 18,780.00 $ 1,576.00 36 [Struct aealtroo! for bieechors muerte 3 740,000.00] 100% 100% | 9 Tavcq000] 8 + | — Tagc0000]% 74,000.00 34 [Struct etpettroo! lor binachers wmiat 3 103.6425 5 & zmoonco Ge [interior wee reptariad $ 78,000.00] 100% woe |S = 7S.s00.00] 5 - |[s 75,000.00 | $ 7,820.00 me | interice wate Wetetation % ea700.00 % . Sic |Specimty Bere materia’ % 2050000] 100% 10% | 28000015 - |s 79,600.00 | 2.060.00 Bd |Specinty hee bial S 7R0N000 ; . Uy 3 zao0.00 s . 100 [Seth accessories ratariat 3 e000R00] 100% wor | 9000000] 5 - fs 90,000.00 | $ @.000.00 10 accessories brestathation 3 15,200.00 3 - We mane 3 e000] 100% 100% $ 4 20000/ 8 - 1s 0000.00] 5 ‘9,480.00 100 |The ietasetion $ enconon B . 2 $ 13600000 $ . 1 orator & $4000.00] 100% oon | % s4.00000] 8 - [s 84,000.00 | $ 6,400.06 12 [Gate instataion 3 9pon09 s . 12e [Concrete and rebar material $ xomc0] 10% 100% | % s200000] 3 - |b 32,000.00 | $ 1.20000 12d [Concrete and rebar ineteietion 4000000 ; : 1s 6 138,000.00 3 : ‘$e & 4gpmncn] 100% won [3 saeooco|s - |e 4g,amn.00 | 8 4.00.00 1 & 7020000 FY - tbe $ srgon0o| 100% won | 8 37,400.00) % - 1s 37,500.00 | $ 3730.00 184 $ 7g0n00 $ . ® $ 185,002.00 s - oa $ Gxordoo| 110% 10% «| 3 53,000.00 - |e 8,000.00 | $ 6,200.00 1% $s @2poo0 “ Lad $ BA30000/)% - [8 $3,300.00 | $ $300.00 18 $ 1800000) 100% woe | s 1500000] 8 - [8 15,000.00 | & 1,800.00 veo $ s00n00 s . 3 5 n 3 330,000.00 s - 200 $ eacmoo| wor won [|S mmcoocots - |s 0,000 00 | $ €,000.00 2 4% 150,000.00 $ : We % 2260000] 100% wor $$ = 2250000]5 - Is 22,800 00 | $ 2,280.00 204 $ 17,500.00 ry . We % 4250000] 100% on | 4780000] 6 $ 42,500.00 | $ 4250.00 a $ = 17,800.00 s + t . 2 3 s6,90n.00 % : a 5 Me raster 4 100% won |3 enoonno] $ + 4s 60,000.00 | & 6,000.00 2b |dechanical fetebeton % Mon P 5 $ . Eid $ 4,100,000.00 3 . 260 [Light Facharen moneriat $ 101,000.00] 100.0% oon «| 8 101,000.00] 5 + [8 — toro0n00]$ = 10,100.00 20> [Were meta $ 1m1.001001 10007% tom =| $ 101,00000]5 += 1% — 191,000.00] 19,100.00 200 Service Entrance material S eao000] 100.0% won 15 s - |t @n.000.00 | $ 2,900.00 20d fConcul maseried $ ee.00n00} 100.0% toon [5 enccono] s s 4,000.00 | § 6.00.00 2be [Diewiouton equiprent $ 101,880.00 3 . 200 |eectrice! labor 6 sxzseo00] 120% | som | inary [8 rasooco|s 8.21.80] 5 TAAT150 632.15 5 . v9 [exmtie % 386,000.00 r 5 26a \Pasrting metetet $ 0580.00} 100.0% wom 14 - 00,830.00 | § 9,055.00 2 PPrurbing labor S zmeasoco] TE0e% 75.00% |3 216,000.00 % 248,000.00 5 F 5 e MARTIN FELD $ . 1 [00% Damion (ARE & Chi-PermivApaovams =| $ © 200,00000 100% 1oo% =| 8 20000000 $ 200,000.00 0 12 ]90% Design $ 30,000.00 100% woo, «| $ «© sacosno $ ‘W.00n00 o 1h [100% Beaign $ = 7500.00 100% 10% [3 = 75000 $ 7,500.00 0 Ye [Adriniatraiion Qing Construction s nso 4s . 2 . . VILLAGE ry 5 1 [40% Omalgn (ARE & Cv}. Perwiiipprovale =| 2 134,000.00 100% 100% | 8 138,000.00 $ 198,000.00 a fa |90% Design $ © 30,000.00 100% worn =| % 20,000.00 3 76,000 00 o 1D }100% Deskn $ = 6500.00 100% ae Ce) $ 5,800.00 O te [Adwiniairation Quting Consanuction 8 £00.00 s . s - & |sTe ry 5 1 [00% Oesign (ARE & Chit}-Perniiatgovals = | $= .200.00 100% wom, 6] 3 05,20000 ‘ €3,200.00 0 1° Cerin $ 190,000.00 100% form «=| $ 11,000.00 3 190,000.00 : 1b |100% Design 3 13,600.00 100% OR FS = 1200000 FY 13,000.60 0 te Durtrg Corsinuction % «20000 2 [Eartveceh & Grading 3 600,000.00 100% woR | soao0ac0 $ $90,000.00 ; 2 [Ste trprovernects $ za 100% wR | 8 z3200825 $ «7280825 O s . © Demotttion Incl Wall, Lights $200,000.00 100% on =|3 200,000.00 $ == 200,000.00 o 6 $ 87,080 100% wou | 3 87,40850 r @7,10060 0 H [ctond Bullder's Rect to 16-34-19 & 20,000.00 100% ox =| 5 200,000.00 $ 280,000.00 0 TOTAL $B. $70.00, TOTS 19119 99] EMMETT IAD On etored al ‘Total Retainage PE” Paul E. Joseph Stadium STORED MATERIAL SUMMARY PE#33 SUBCONTRACTOR OR] OPENING ADDITIONS THIS | USAGE THIS CLOSING TEM} Description SUPPLIER INVENTORY PERIOD PERIOD INVENTORY Electrical Room Site 1_|Eaton POW-R-tine Equipment] U&W inv#4178 $___ 104,850.00 -_|s____ 101,850.00} $ 101,850.00 Totals $104,850.00 -_|s 101,850.00] 101,850.00 U&W PO Box 1720 Kingshill, USVI, 00854 Ph: 340-778-0012 Fax: 340-778-2545 emait: kiustig@gecusvi.com GEC, LLC (Paul E.Joseph Stadium) DATE P.O. Box 1656, Kingshill 02/26/2021 St. Croix, VE 00851 INVOICE NO. 14178 * ATTENTION: CUSTOMER #: 0000522 Ship Vis: None Customer PO #: Item # Description Ordered Price Each 01 Eaton POW-R-LINE Equipment 0.00 0.00 02 MODP-FH ( Main Distribution Panel - 1.00 49,230.00 Electric Room) with breakers per Drawing E3.2 03 PNL-CL1 ( Concession 1 Panel) with 4.00 1,650.00 breakers per Drawing E3.2 04 PNL-CL2 ( Concession 2 Panel) with 4.00 1,650.00 breakers per Drawing E3.2 05 PNL-FHE ( Electric Room Panel) with 1.00 9,330.00 breakers per Drawing E3.2 06 PNL-FH { Electric Room Panel) with 1.00 - 12,030.00 breakers per Drawing E3.2 07 PNL-FLE ( Electric Room Panel) with 1.00 675.00 breakers per Drawing £3.2 08 PNL-FL ( Electric Room Panel) with 1.00 3,360.00 breakers per Drawing E3.2 a9 PNL-FTL ( Electric Room Panel) with 1.00 11,370.00 breakers per Drawing £3.2 40 -MDP-LH ( Electric Room Field Lights 1.00 11,400.00 Panel) with breakers per Drawing E3.2 41 MPZ-LL ( Concession 1 Restrooms, hand 1.00 1,155.00 dryers,scoreboard control) with breakers per Drawing E3.2 DUE THIS INVOICE THANK YOU Amount 0.00 49,230.00 1,650.00 1,650.00 9,330.00 12,030.00 675.00 3,360.00 11,370.00 11,400.00 1,155.00 $101,850.00 [Change Order 16 t0 PE) Contract Payment Deteie eee TE ee ee PE Maweh he Co so tmnans OPE 1 oem tno ted ™ GOVERNMENT OF THE VIRGIN ISLANDS OF THE UNITED STATES Department of Property and Procurement 8201 Sub Base, 3rd Floor, St. Thomas, U.S. Virgin Islands 00802 3274 Estate Richmond, Christiansted, U.S. Virgin Islands 00820 St. Thomas: | St. Croix: Main Office: (340) 774-0828 Main Office: (340) 773-1561 Fax: (340) 777-9587 www.dpp.vi.gov Memorandum: To: From: Date: Re: xc: Nathan Simmonds Director, Finance and Administration Virgin Islands Public Finance Authority Anthony D. Thomas Mba DE Oe Commissioner Department of Property & pik rernent March 23, 2022 Request for Payment to GEC, LLC Transmitted herewith for partial payment is Periodical Estimate No. Thirty-Four (34), for Construction Services rendered by GEC, LLC, for the Design/Build for Paul E. Joseph Stadium & Sports Complex, St. Croix, Virgin Islands as outlined in Contract No. C003SPRC1I5(GEC). Estimate Number Date Amount P.E. #34 March 8, 2022 $51,568.96 Funding Source: 2014C Gross Receipt Tax Bond Department of Sports, Parks & Recreation Department of Public Works Department of Property and Procurement Contract File ADT/klp/te GOVERNMENT OF THE VIRGIN ISLANDS OF THE UNITED STATES Department of Property and Procurement 8201 Sub Base, 3rd Floor, St. Thomas, U.S. Virgin Islands 00802 3274 Estate Richmond, Christiansted, U.S. Virgin Islands 00820 St. Thomas: St. Croix: Main Office: (340) 774-0828 Main Office: (340) 773-1561 Fax: (340) 777-9587 www.dpp.vi.gov March 23, 2022 John R. Wessel Managing Member GEC, LLC P.O. Box 1656 Kingshill, V1 00851 RE: APPROVED PERIODICAL ESTIMATE NO. 34 C003SPRCI5 (GEC) - Design/Build for Paul E. Joseph Stadium & Sports Complex, St. Croix, Virgin Islands Dear Mr. Wessel: Transmitted herewith approved is Periodical Estimate for Partial Payment Number Thirty-Four (34), dated March 8, 2022, and received on March 22, 2022, relative to the above referenced contract. The periodical estimate is the balance due on this contract in the amount of Fifty-One Thousand, Five Hundred Sixty-Eight Dollars and Ninety-Six Cents ($51,568.96). Respectfully, Hdliny 0. Ghar Anthony Qf Thomas Commissioner ADT/kip/tc xe: Department of Sports, Parks & Recreation Department of Public Works Virgin Islands Public Finance Authority Department of Property and Procurement Contract File