CONSTRUCTION CONTRACT THIS CONTRACT (the “Contract”) is made this day of _. , 2018 in the Territory of the Virgin Islands, by and between the G Government of the Virgin Islands, Department of Property & Procurement, on behalf of the Department of - Edueation of 1834 Kongens Gade, St. Thomas, U.S. Virgin Islands 00802 (heremafter referred to as “Government” or “VIDE”) and AECOM Caribe LLP (hereinafter referred to as “Contractor” or “AECOM”) of 72 Kronsprindsens Gade. Suite A,.St. Thomas, U.S. Virgin Islands 00802. The Government and Contractor are each a “Party” and are collectively the “Parties” to this Contract. WHEREAS, the Government is in need of a contractor to furnish all labor, materials and equipment necessary for the Purchase and Installation of Four (4) Temporary Classrooms on the Island(s) of St. Croix and St. Thomas as more particularly described in Addendum I, (Scope of Work/ Basis of Estimate/ Basis..of Design) (the “Services”); and. _'WHEREAS, the Services were solicited by the VIDE pursuant to 31 V.LC §239 (a)(1); and WHEREAS, the Contractor represents that it is willing and capable of providing such Services; and NOW, THEREFORE, in consideration’ of the mutual covenants herein contained, and intending to. be legally bound by this written instrument, the Parties covenant and apree as follows: 1. SERVICES 1.1 The Contractor will provide the Services described more particularly in Addendum I (Scope of Work, Basis of Estimate/ Basis of Design) incorporated herein by reference and made. a part of this Contract. 1.2 The Services. include the construction and installation. of four (4) temporary classrooms and structures at two (2) school sites .on the island of St. Thomas, and two 2) school sites.on the island of St. Croix (each, a “Site” and collectively the “Sites”) in. the U.S. Virgin Islands (hereinafter referred to as the “Project”). The temporary classrooms will be provided in the form of pre-manufactured modular buildings that will be factory constructed and delivered and installed on the Sites approved by the Government. 1.3 The Services, the Contract Sum, and the Contract Time are all based on the Government’s. criteria and on the information and assumptions in the details contained in Addendum I (Scope of Work/Basis of Estimate/Basis of Design), which addendum incorporates Contractor's Basis of Estimate and Basis of Design. The Parties agree that Contractor shall be entitled to Change Orders adjusting the Contract Time and Contract Sum if there are any requested or required changes in the Services that increase the cost or time to perform the Services, including but not limited to changes to the site plans, layouts, quantities, building selections, space planning, and/or programming, or other details and/or assumptions set forth in Addendum I (Scope of Work/Basis of Estimate/Basis of Design). Change Orders which would increase the Contract Time or Contract Sum are subject to the review and approval by the Government. 1.4 The Parties shall, in good faith, negotiate such Change Orders and agree that corresponding adjustments to the Contract Sum and Contract Time shall be evaluated based upon a comparison of: (a) the initial Basis of Design, Basis of Estimate, and cost proposal in Addendum | (Scope of Work/Basis of Estimate/Basis of Design): to (b) Contractor’s updated Basis of Design, Basis of Estimate. and cost proposal after incorporating the requested or required change(s), 2 TERM cl This Contract shall commence immediately upon execution of the Contract by the Governor (the “Commencement Date”) and shall terminate on December 15, 2018 (Final Completion Date), or upon the Contractor obtaining full compliance of the terms of this Contract, whichever occurs earlier. 2.2 The Contract Time is defined as the period starting on the Commencement Date and ending December 15, 2018. < 17, TERMINATION FOR CONVENIENCE; SUSPENSION 17.1 The Government will have the right to terminate this Contract in whole or in part, without cause on ten (10) days written notice to the other party specifying the: date. of termination.. If Government terminates this Contract for convenience and without cause, Contractor shall be shall be compensated for Services performed prior to termination, plus any other expenses attributable to termination, including but not. limited to demobilization costs, early-termination and/or cancellation fees applicable to executed subcontracts and purchase orders: in accordance with the provisions. of Addendum III (Termination) attached hereto and made a part hereof. 17.2 If the Government fails to make payments to the Contractor in accordance with this Contract and Addendum IV, such failure shall be considered substantial. nonperformance and cause for termination. or, at the Contractor’s option, cause for suspension of performance of the Services. If Contractor elects to suspend the Services, the Contractor shall give seven days’ written notice. to the Government before ‘suspending the Services. In the event of a suspension of the Services, the Contractor: shall have no liability.to.the Government for delay or damage caused by the suspension of the Services. Before resuming the Services, the Contractor shal! be paid all sums due prior to suspension and any expenses incurred in the interruption and resumption of the Services. The Contract Sum and Contract Time shall thereafter be equitably adjusted ‘through a Change Order. 17.4 If the Government suspends the Project, the Contractor shall ‘be compensated. for the Services performed prior to notice of such suspension. When the Project is ‘resumed, the Contractor shall be compensated for expenses incurred in the interruption and resumption of the Contractor’s Services. The Contract Sum and Contract Time shall thereafter be equitably adjusted, provided the suspension was through no fault of the Contractor. 17.5 If the Government suspends the Project for more than 45 cumulative days for reasons other than the fault of the Contractor, the Contractor may terminate this Contract by giving not less than ten (10) days’ written notice. 18. PARTIAL TERMINATION. The performance of work under this contract may be terminated by the Government in part, whenever the Government shall deem such termination advisable.. This: partial termination shall be effected by delivering to the Contractor a Notice of Partial Termination. specifying. the extent to. which the term and/or duties under this contract are terminated and the date upon. which such termination becomes effective. The Contractor. shall be entitled to receive payment for services provided to the date of termination, including payment for the period of the ten (10) days notice. 19. NON-DISCRIMINATION Contract No. Contractor's Initiats ak COOZ2D0ETI9 No person shall be excluded from participating in, be denied the proceeds of, or ‘be subject to discrimination in the: performance of this Contract on account of race, creed, color, sex, religion, disability or national origin.. ‘20. CONFLICT OF INTEREST 20.1 Contractor covenants that it has no interest and will not acquire any interest, direct or indirect, which would conflict in any manner or degree with the ‘performance of services required to perform under this Contract. 20.2 Contractor further covenants that it is: (a) _not 4 territorial officer or employee (i.e., the Governor, Lieutenant Governor, member of the Legislature or any other elected. territorial official; or an officer or employee of the legislative, executive, or judicial branch of the Government or any agency, board, commission, or independent instrumentality of the Government, whether compensated ona salary, fee or contractual basis); or (b) _a territorial officer or employee and, as. such, has: (i) familiarized itself with the provisions of Title 3, Chapter 37, Virgin Islands Code, pertaining to conflicts of interest, including the penalties. provisions set forth in section 1108 . thereof, . {ii) not made, negotiated or influenced this contract, in its official , capacity; (iii} no financial interest in the contract as that term is defined in section 1101, (1) of said Code chapter. 21. EFFECTIVE DATE The effective date of this Contract is upon the execution by the Govemor of the U. S. Virgin Islands. 22, NOTICE Any notice required to be given by the terms of this Contract shall be deemed to. have been given when the same is sent by certified mail, postage prepaid or personally delivered, addressed to the parties as follows: GOVERNMENT Lloyd T. Bough, Jr. Commissioner Department of Property and Procurement #3274 Estate Richmond, St. Croix g Contract No. Contractat’s wie U. S. Virgin Islands 00820-4241 Sharon Ann McCollum, Ph.D. Cominissioner Department of Education 1834 Kongens Gade St. Thomas, U. S. Virgin Islands 00802 CONTRACTOR. Steven Richards Authorized Representative. AECOM Caribe, LLP 6200 South Quebec Street Greenwood Village, CO 80111 23. LICENSURE The Contractor covenants that it has: a. obtained all of the applicable licenses. or permits, temporary or otherwise, as required by Title 27 of the Virgin Islands Code; and b. familiarized itself with the applicable provisions of Title 27 of the Virgin Islands Code pertaining to professions and occupations. 24. CONTRACTOR’S REPRESENTATIONS. _ 24.1. The Contractor agrees that he is fully informed regarding all the conditions affecting the work to be. done and labor and materials.to be furnished for the completion of the Contract, and that he has been engaged in and now does such work and represents | that he is fully equipped, competent, and capable of performing the work and ig ready and willing to.perform such work. 24.2 The Contractor agrees further to begin work not later than. the. date indicated on the formal notice to proceed and complete the work by December 15, 2018. 24.3. The Work shall be done under the direct supervision of the Government, and in accordance with the laws of the Government and it Rules and Regulations thereunder issued and any and all applicable federal rules and regulations. The parties hereto agree. that this contract shall, in all instances, be governed by the Laws of the Government of the U.S. Virgin Islands. Contract No. Contractor’s Initials 2° COOZD0ETI9 (25. WARRANTY OF NON-SOLICITATION 25.1 The Contractor expressly warrants that he has employed no. person to solicit. or obtain this contract on his behalf, or to cause or procure the same to be. obtained upon ‘compensation in any way, contingent, in-whole or in part, upon such procurement, and that he has not paid, or promised or agreed to pay to any person, in consideration of such procurement, or in compensation for services in connection therewith, any brokerage, commission, or percentage upon the amount receivable by him hereunder; and that he has not, in estimating the contract price demanded by him included any sum by reason of such brokerage, commission or percentage; and that all monies payable to him hereunder are free: from obligation to any other person for services rendered, or supposed - to have been rendered, in the procurement of this contract. 25.2. Breach of the warraiity shall give the Government the right to terminate this Contract, or in its discretion, to deduct from the contract price or consideration the amount of such commission, percentage, brokerage or contingent fees. Contractor warrants that it shall not, with respect to this Contract, make or Present any claim upon or against the Government. of the U.. S. Virgin Islands, or any officer, department, board, commission, or other agency thereof, knowing such claim to be false, fictitious or fraudulent. Contractor acknowledges that making such a false, fictitious, or fraudulent claim is an offense under U.S. Virgin Islands law. 27. DEBARMENT CLAUSE By execution of this contract, the Contractor certifies that it is eligible to receive contract awards using federally appropriated funds and that it has not been suspended or debarred from entering into contracts with any federal agency. The Contractor shall include this provision in each of its subcontracts hereunder and shall furnish its ‘subcontractors with the current “LIST OF PARTIES EXCLUDED FROM FEDERAL PROCUREMENT OR NON PROCUREMENT.” In the event the Contractor or any subcontractor misrepresents its eligibility to receive contract-awards using federal funds, ‘the Contractor or subcontractor agrees that it shall not be entitled to payment for any work performed under this contract or any subcontract and that the Contractor ot subcontractor shail prompily reimburse the Government of the Virgin Islands for any ‘progress payments heretofore made. 28 NOTICE OF FEDERAL FUNDING Contractor acknowledges that this Contract is funded, in whole or in part, by federal funds. Contractor warrants that it shall not, with respect to this Contract, make or present any claim knowing such claim to be false, fictitious, or fraudulent. Contractor acknowledges that making sucha false, fictitious, or fraudulent claim is a federal offense. coo2zD0r TI? Contractor's Initiats_ SO \ 29. DAVIS BACON ACT Contractor herby agrees that it shall comply with all rulings and interpretations of the Davis-Bacon Act (40 USC 276a-5) and AECOM agrees that all employees shall be paid the local prevailing wages as established by Virgin Islands states and laws. 30. CERTIFICATION OF EMPLOYMENT Contractor herby agrees that pursuant to 31 V.LC 236(h) it will hire at least two individuals from the Welfare to Work program administered by the Labor and Human 31.1 Neither Party shall be liable to the other for any delays or failure to perform under this Contract, as a result of conditions reasonably beyond the Party’s control including but not limited to war, terrorist acts, riot, strikes, fire, earthquakes, hurricanes, floods, or any act of God, discovery or uncovering of hazardous. or toxic materials or historical artifacts-at the Project sites, unusually severe: ‘weather, acts of terrorism, sabotage, embargo, energy shortage, wreck or delay in transportation, accidents: in the handling and rigging of heavy equipment, explosion, riot, war, court injunction or order, delays by or acts or orders of any governmental body or changes in laws or government regulations, acts or omissions of the other Party or its other contractors, consultants, or representatives. 31.2 If Contractor is delayed at any time in the commencement or progress of the Services by an act or neglect of the Government, or by a consultant, representative,-or separate contractor employed by the Government, including but sot limited to: (a) Government’s. failure to timely perform its obligations under this Contract; or (b) Government’s failure to timely review and approve any submittals or design documents related to the Sites; or (c) changes ordered in the Services:by the Government; or (d) any force majeure event listed in Paragraph 31.1; then the Contract Time shall be extended by Change Order for a period of time reasonably necessary 10 overcome the effect of the delay, and the Contract Sum shall. be increased for the additional costs (if any) arising from such delay. 32.. SEVERABILITY: Tf any of the provisions of this Contract are détermined.to be invalid, such invalidity shall not affect or impair the validity. of the other provisions, which shall be considered severable and shall remain in full force and effect. 33. CONCEALED OR UNKNOWN CONDITIONS 1! COOZ2D0ET19 » 33.1 If the Contractor encounters conditions at any of the sites that are (1) subsurface or otherwise concealed physical conditions that differ materially from those indicated in the Contract Documents; or (2) unknown physical conditions of an unusual nature that. differ materially from those ordinarily found to exist and generally recognized. as inherent in construction activities of the character provided for in the Contract Documents, the Contractor shall. promptly provide notice to the Government before conditions are disturbed and in no event later than three (3) days after first observance of the conditions. The Government shall promptly investigate such conditions and, if the Government determines that they differ materially and cause an increase or decrease in the Contractor’s cost of, or time required for, performance of any part of the Services, shall recommend an equitable adjustment in the Contract Sum or Contract Time, or. both. If the Government determines that the conditions at the site are not materially different from: those indicated in the Contract Documents and that no. change in the terms of the Contract is justified, the Government shall promptly. notify the Contractor in writing, stating the reasons. 33.2 If, in the course of the Services, the Contractor encounters human remains, or recognizes the existence of burial markers, religious sites, archaeological sites, or wetlands, not indicated in the Contract Documents, the Contractor shall immediately suspend any operations that would affect them and shall immediately notify the ‘Government. Upon receipt of such notice, the Government shall promptly take any action necessary to obtain governmental authorization required to resume the operations. The Contractor shall continue to suspend such operations until otherwise instructed by the Government but shall continue with all other operations that do not affect those remains or features. Requests for adjustments in the Contract Sum.and Contract Time arising from the existence of such remains or features may be made as provided in Paragraph 35.. 33.3. The Government acknowledges. and agrees that, prior to commencing the Services, Contractor has not created or contributed to the creation or existence of any air, subsurface, ground, or other environment. hazards, contamination, or pollution, or the “presence of hazardous, toxic, or contaminated substances and materials, (collectively, the “Pre-Existing Conditions”), Contractor assumes no title, ownership of, or liability or responsibility under this Contract.for the creation, existence, or presence of any Pre- Existing: Conditions. ‘To the extent Contractor incurs. any losses, damages, costs, penaltiés, fines, and expenses, including reasonable attomeys' fees, of any kind or character. arising from or relating to Pre-Existing Conditions. (collectively “Environmental Losses”), Contractor shall be entitled to.a Change Order increasing the ‘Contract Sum by the amount of such Environmental Losses in accordance with Paragraph 33.4 The Government further represents that it shall immediately notify Contractor of any information, data, or documents in the possession of or reasonably -known to the Government relating to subsurface conditions affecting any Site. The Government further agrees to advise Contractor prior to the commencement of Services of the existence of dust, fumes, gas, noise, vibrations, or other particulate or known particulate matter at or near a Site that may create or contribute to a potential health Contractor's Initials Contract No. coozdoL ii? La hazard or nuisance to persons working within the area and the existence and identity of any known or suspected hazardous or toxic substances, waste, or other hazards or hazardous conditions that may pose a threat to human health, safety, or the environment if reasonably known to the Government. If the foregoing conditions are encountered during the course of Contractor's Services, the Government agrees that the Contract Sum, Contract Time, and/or any other appropriate terms and conditions of the Contract may be equitably adjusted in accordance with a mutually agreed upon, written Change Order. 34. GOVERNMENT REQUIREMENTS 34.1 The Government shail promptly obtain easements, zoning: variances, and legal authorizations and approvals or entitlements regarding site utilization where essential to the execution of the Services. 34.2 The Government shall cooperate with the Contractor in securing building and other ‘permits, licenses and inspections. Local permitting fees will be waived including fees for Building and Earth Change’and Coastal Zone Management. 34.3 The Government shall review and approve or take other appropriate action on submittals and any other design/construction documents and deliverables that require Government review and/or approval with reasonable promptness and within such time period(s) so as not to delay the progress of the Services. Government shall also schedule and conduct all reviews, inspections, and tests required to obtain certificates of occupancy at the sites and/or any equivalent certifications from. any third party and/or governmental entities with jurisdiction, within the durations and deadlines set forth in the Addendum I. If Government dees not perform its obligations in this Paragraph 34,3 by the deadlines set forth in the Addendum I. Contractor may be entitled to an extension of the Contract Time for such delays, occasioned by the Government’s actions and may also be entitled to an increase in the Contract Sum to the extent such delays result in increased costs to perform the Services. The Government’s review shall not constitute approval of safety precautions or, unless otherwise specifically stated by the Goverment, of any construction means, methods, techniques, sequences or procedures, The Government approval of a specific item shall not indicate approval of an assembly of which the item is a.component. 35.1 Changes in the Services may be accomplished after execution of the Contract, and without. invalidating the Contract, by Change Order subject to the limitations stated in this Contract and this Paragraph 35. A Change Order shall be based upon a written agreement signed by both Parties. 35.2 A Change Order is a written instrument signed. by the Government and Contractor stating their agreement upon the change in the Services, and the amount of the Contract No. . Contractor's Initials ~~ COO2ZD0ETI9 adjustment, if any, in the Contract Sum and Contract Time. Contrector shall have no. obligation to proceed with changed work or services without an executed Change Order. 35.3. The adjustment to the Contract Sum and ‘Contract Time shall, when applicable, be evaluated under and based upon Addendum .I (Scope of Work/Basis of Estimate/Basis of Design), and such adjustment shall be calculated on one. of the: following methods: (a) | Mutual acceptance of a lump sum properly itemized and supported by sufficient substantiating data to permit evaluation; (b) Unit prices. stated in the Contract Documents or subsequently agreed upon; or | — {c) Cost to be determined in a manner agreed upon by the parties and a mutually acceptable fixed or percentage fee. 35.4 If the Parties are. unable to agree on the method for adjustment in to the Contract Sum or Contract Time, the Government. shall determine the method and the adjustment on the basis of reasonable expenditures and savings ‘of those performing the Services attributable to the change, including, in case of an increase or decrease, an amount for overhead and. profit in the percentages. set forth in the Basis of Estimate. In such case, Contractor ‘shall keep and present, in. such form as the Goverument may prescribe, an itemized accounting together with appropriate supporting data. 35.5 Unless otherwise provided in the Contract Documents, costs for the purposes. of subparagraph 35.4 shall be limited to the following: Additional costs or reduction of costs of construction services including but not limited to costs of materials, supplies, and equipment. including cost of transportation, whether incorporated or consumed; rental costs of machinery and equipment, exclusive of hand tools; unforeseen work and additional costs of supervision, labor, and field office. personnel directly attributable to the change. 36. CONTRACTOR’S WARRANTY 36.1 The Contractor warrants to the Government that, for a period beginning on the date Contractor commences the Services and terminating one year from acceptance of the final product, materials and equipment furnished by Contractor under the Contract will be of good quality and new unless the Contract Documents require or pennit otherwise. The Contractor further warrants that, for a period beginning on the date. Contractor commences work and terminating one year from the date of completion of the applicable Sites, the Services will conform to the requirements of the Contract ‘Documents. Services, work, materials, or equipment not conforming to these requirements may be considered “Defective Work.” The Contractor’s warranty excludes. remedy for damage or defect caused by abuse, alterations not executed by the Contractor, improper or insufficient maintenance, improper operation, or normal wear and tear and normal, usage. If required by the Government, the Contractor shall. furnish satisfactory evidence as to the kind and quality of materials and equipment. Contract No. Contractor's Initials COOZD0ETI9 36.2 Upon written notice from the Government of Defective Work, the. Contractor shall either correct all Defective Work, whether or not fabricated, installed or completed, or, if the Defective. Work has been rejected by the Government, remove it from the applicable Site(s) and replace it with conforming work. The Contractor shall bear all direct, indirect and consequential costs of such correction or removal (including, but not limifed to fees and charges of engineers, architects, attorneys and other professionals) made necessary thereby, and shall hold the Government harmless for same. 36.3. Should the Government determine, at its sole discretion, it is in its best interest to accept Defective Work, the Government may do so. Contractor shall bear ail direct, indirect and consequential costs attributable to the Government's evaluation. of and determination to accept defective Work. If such determination is rendered prior to final payment, a Change Order shall be. executed evidencing such. acceptance of such. Defective Work, incorporating the necessary revisions in the Contract Documents and, if appropriate and justified, reflecting an appropriate decrease. in the Contract Amount. If the Government accepts such Defective Work after final payment, the Parties shall negotiate in good faith in an attempt to. agree upon an appropriate amount to adequately compensate the Government for its acceptance of the Defective Work. Notwithstanding any provision to the contrary in this Contract or other Contract Documents, the Contractor and Government waive all claims against each other, and shall have no liability, for consequential, indirect, incidental, punitive, or exemplary damages of any kind or nature whatsoever arising out of or relating to this Contract. This mutual waiver includes but is not limited to: (a) damages incurred by the Government for rental expenses, for losses of use, income, profit, financing, business and. reputation, aud for loss of. ‘management or employee productivity or of the services of such persons; and (b) damages incurred by the. Contractor for principal office expenses including the compensation of personnel stationed there, for losses of. financing, business and reputation, and for loss of profit except anticipated profit arising directly from the Services. 38. DEFAULT AND FAILURE TO PERFORM 38.1. The Government may terminate the Contract, in whole or in part, for default in the event of any material failure or refusal of the Coritractor to perform its obligations under this Contract. Upon the. occurrence of an event of default, the Government shall provide Contractor written notice describing the factual and contractual bases of the default and providing Contractor an opportunity to cure, or complete a cure ° oh Contract No. Contractor's Initials —_. LO02D0E Tig within 7-days of such notice. If Contractor fails to cure, or fails to reasonably commence to cure the default within such 7-day ‘period, Government may provide notice of termination of the Contract by providing Contractor with ten (10). days written notice. 38.2 Upon termination for Contractor’s default, the Parties agree that. the provisions of 31 V.LR. & Regs. § 242-88 shall apply with respect to the costs, charges, and damages. recoverable by Goverment, and/or payable to Contractor. Upon such termination for default, whether in. whole or in part, Contractor shall ‘be entitled to receive payment for Services performed through the date of termination, In addition, the post- termination procedures set forth in. Addendum III, section (a) shall apply. 38.3 If Government fails to pay amounts when due (and does.not provide notice of any ‘withholding pursuant to this Contract), or has repeatedly failed to fulfill the Government’s obligations under the Contract, the Contractor shall provide. Government written notice of the default and providing Government an opportunity to cure within 7- days of such notice..If Government fails to cure, or fails to reasonably commence to cure the default within such 7-day period, Contractor may provide notice of termination of the Contract by providing Government with ten (10) days written notice. 39, LIABILITY INSURANCE 39.1 The Contractor shall provide the Government with proof of Commercial General Liability Insurance coverage and Professional Liability coverage for the entire period of this Contract. The Contractor shall be insured under each policy in an amount of not less than ONE MILLION DOLLARS AND ZERO CENTS (51,000,000.00) for each occurrence. In the event that the Contractor’s existing coverage wiil expire before. the.end of the term of this Contract, the Contractor shall provide proof of the renewal of coverage within ten (10) days after beginning of the new period of the insurance. The policies shall be maintained. with insurer(s) and in a form satisfactory to the Government, and the Contractor shall submit a Certificate of Liability Insurance and Declaration/Endorsement pages naming the Government as-an additional insured and certificate holder on the Commercial General Liability Policy. 39.2 WORKERS’ COMPENSATION: Contractor shall: ‘supply proof of current coverage under the Government Insurance Fund as required under 24 V.LC. § 272. 40. OTHER PROVISIONS: 40:1 The “Contract Documents” include this Contract, any amendments and executed Change Orders, Addendum I, (Scope of Work/ Basis of Estimate/ Basis of Design), Addendum Hf (General Provisions and Warranties together with the. additional General Provisions — Construction), Addendum DI (Termination of Contracts), and. Addendum IV (Compensation) and Addendum V (Additional Terms: and Conditions attached hereto. The Contract Documents are attached hereto, made a part of this Contract and are: incorporated. herein by reference.. 16 -_ Bi . Contract No. COOZD0E T4195 Contractor’s Initials, IN WITNESS WHEREOF, the parties intending to be legally bound have hereunto set their hands on the day and year first above written. WITNESSES: GOVERNMENT OF THE VIRGIN ISLANDS DEPARTMENT OF PROPERTY AND PROCUREMENT ou: Lip “ Lloyd T. Bough, Jr. Commissioner DEPARTMENT OF EDUCATION (otal § LD edt Po pal Commissioner j CONTRACTOR ' AECOM Caribe, LLP ft / \ A ri f a *- eee i Ma Se age, Daa II6 : Steven Richards — Authorized Representative (Corporate seal, if Contractor is a Corporation) Date: 0 “0 |=] 4 APP Kenneth E, Governor of the U.S. Virgin Islands APPROVED AS TO LEGAL SUFF yy Department of Justice: i 4 Date: | | ce 4 | q Assistant Attomey General Purchase Order No. * me Contract No. Contractor's Initials COO2D0ETI9 I hereby that this is a true and exact copy of Contract No. entered into between the Department of Property and Procurement, on behalf of the Department of Education and AECOM Caribe, LLP four Gre— Lloyd T. Bough, Jr. Department of Property and Procurement » wh = COO7D0F T 9 Contractor’s Initials