r •TGERAGHTY & MILLER, INC. Environmental Services Ground Water Engineering Hvdrocarbon Remediation Education September 14, 1992 Ms. Caroline Kwan, Project Manager USEPA-Region II 26 Federal Plaza, Room 737 New York, NY 10278 Dear Ms. Kwan: On behalf of Ms. Ana Gloria Ramos, Designated Coordinator for the Tutu Environmental Investigation Committee (TEIC), we are sending you a revised schedule for the upcoming field work at the Tutu Service Station Remedial Investigation. The revised schedule reflects changes requested by the U.S. Environmental Protection Agency (USEPA). If you have any questions, please call. c: Ana Gloria Ramos - TEIC Jose Agrelot - Soil Tech DN/intb #PR01301-3/091192c.ltr Sincerely, GERAGHTY & MILLER, INC. Thomas V. Danahy Scfentwt/Pjoject Manag Daniel A. Nachman Project Director/Project Officer TUT 006 1737 201 West Passaic Street, 3rd Floor • Rochelle Park, New Jersey 07662'(201) 909-0700* FAX (201) 909-0567/0568 *64878* 64878 Table 1. Anticipated Schedule for August through November 1992, Tutu Service Station Investigation, St. Thomas, " U.S. Virgin Islands. Date Activity August 24 — September 16 August 24 — September 18 September 14 — September 16 September 19 — September 27 Monday, September 28 September 28 - October 9 October 9 - October 14 October 15 - October 16 October 16 - October 28 Thursday, October 29 Friday, October 30 Monday, November 2 @ 10:00 a.m. Tuesday, November 3 @ 10:00 a.m. Friday, November 6 Monday, November 9 @ 10:00 a.m. Tuesday, November 10 @ 10:00 a.m. Finish monitoring well installation; including MW-2, MW—5, MW-6R (replacement well), and MW—9S (additional well); abandonment and sealing of MW-6. Development of 19 monitoring wells. The 7th sampling of existing supply wells (pursuant to Administrative Order No. II - CERCLA 00401 and RCRA - 90 - UST - 9003 - 0401). Allow monitoring wells to stabilize. Collect synoptic round of water-levels at all 19 monitoring wells. First ground—water sampling of all 19 monitoring wells. Long—term ground—water level recording to check for possible influence from pumping wells. Review long-term data. Coordinate/prepare for pumping test. Set-up water-level recorders for pre-pumping trend. 4-hour step-test at MW-9orMW-10; record recovery. Set-up recorder for pre—pumping trend for November 2 test Start 24-hour pump test at MW-9 or MW-10; pumping rate to be determined from the results of October 30 step-test. End test; record recovery; data analysis. 4-hour step-test at MW- 10D; record recovery. Set—up recorder for pre-pumping trend for November 9 pump test. Start 24—hour pump test at MW- 10D; pumping rate to be determined from November 6 step-test. End test; record recovery. #PR01301/82192tbl.wk3 GERAGHTY & MILLER, INC. TUT 006 1738