GOVERNMENT OF THE VIRGIN ISLANDS OF THE UNITED STATES Public Services Commission IN RE: Docket No. 621 THE APPROVAL AND INTERCONNECTION Order No. 26/2014 OF RENEWABLE ENERGY PROJECT OF THE VIRGIN ISLANDS WATER AND POWER AUTHORITY ORDER WHEREAS, on October 3, 2012, the Virgin Islands Public Services Commission (hereinafter “the Commission” or “PSC”) received an application from Tibbar Energy, USVI, LLC (hereinafter “Tibbar”) for certification of a qualified small power generation facility for a biomass (Agricultural Energy Crop) to renewable energy project in the United States Virgin Islands; and WHEREAS, on December 17, 2012, Gerogetown Consulting Group, the Commission’s technical consultants, submitted a report on the qualified facility application of Tibbar; and WHEREAS, on December 18, 2012, the Commission met in regular session and deemed that Tibbar’s application was complete and in compliance with Chapter 2 of Title 30 of the Virgin Islands Code; and WHEREAS, on January 11, 2013, the Commission APPROVED Tibbar’s application in Order No, 23/2013, Docket 611; and WHEREAS, Tibbar and the the Virgin Islands Water and Power Authority (hereinafter “the Authority” or “WAPA”) have subsequently negotiated the terms of an interconnection agreement and a Power Purchase Agreement; and WHEREAS, on August 13, 2013, the Authority petitioned the Commission for approval of a Power Purchase Agreement between the Authority and Tibbar for the purchase of electric energy for the territory of the Virgin Islands through the development of a renewable energy project; and WHEREAS, on December 19, 2013, the Commission met in regular session at its both offices on St. Thomas and St. Croix; and WHEREAS, after review of the application and deliberation, the Commission voted to continue this matter at the next meeting, to permit time for the PSC’s staff and consultants to